Construction on Center Street (65th - 76th)

City of Milwaukee starts paving of Center Street and when to expect closures
Post Date:04/25/2019 1:00 PM

center streetDid you know that Center Street east of 76th Street is half in Wauwatosa and half in Milwaukee? We partnered with Milwaukee on roadwork on Center Street last year. Last fall, the City of Wauwatosa repaired sanitary and storm sewers, relined sewers, reconstructed some curb ramps, and repaired our portion of Center Street.

The City of Milwaukee will be starting paving on Monday, April 29. Center Street will be closed from 60th to 68th Monday and possibly Tuesday. Center Street from 68th to 75th will be closed possibly Tuesday and Wednesday.

This work is weather dependent. There is rain in the forecast, so there might be a delay. However, you can anticipate three or four days of closures on Center Street.

 