Update as of November 11, 1:30 pm
Please note there is a date change on the final paving of the road. Due to the wet conditions on the road, the contractor is planning to finish the final surface of the road on Wednesday, November 20.
We sent the update below this morning.
- - - - - -
Original message
Work Schedule
The contractor is scheduled to finish the final surface on the road tomorrow (Tuesday, November 19), weather-dependent. This will be similar to the first layer of paving they did. They will start close to 7am and surface the roads all day. You will be able to access the road at night a few hours after they complete the paving operation to allow the asphalt to cool sufficiently.
Other work scheduled for this week include pouring remaining driveway approaches, placing topsoil in the holes present from previous work, and putting in street signs.
Leaf collection
We are planning a special leaf collection in your neighborhood during the week of November 24. You can start raking after the final surface is done on the street. Please have your leaves raked on the street by November 24.
Thanksgiving
We estimate that driveways will be complete by the end of this week, weather dependent. At the latest, driveways will be completed before Thanksgiving. Our contractor will not work on Thursday, November 28.
2020 Work
In 2020, we will replace the remaining sidewalk that was planned on this project and restore lawn areas with sod.