Welcome! Below you will find news articles updating you on the milestones of major public construction projects, such as reconstruction underway and also less sporadic updates on smaller projects, such as repaving. You can also sign up to have these updates emailed directly to you through the subscription tool at the bottom of the page. 

Wauwatosa, Melrose, and Rogers Avenues

Post Date:04/27/2020 1:39 PM

Hi there,

You’re receiving this email because you’re subscribed to the general construction list. We send bi-weekly updates about the construction project on Wauwatosa, Melrose, and Rogers Avenues. Then we will send occasional updates about other city construction projects on a milestone basis.

Wauwatosa, Melrose and Rogers Avenues – Schedule in the next few weeks

The contractor is planning to pave the trench for the water main connection near the intersection of Milwaukee and Wauwatosa Avenue this week, weather-dependent. Until then, there will be road plates to maintain traffic and access at this intersection.

The contractor is also continuing north with storm sewer work. Utility work will continue for at least another month. If you have plans to replace your privately owned water lateral, now is the time to finalize those plans. Please contact Nick Deming, City of Wauwatosa Construction Manager, as soon as possible if you are replacing your privately owned water lateral: ndeming@wauwatosa.net or (414) 479-3541.

The contractor will also likely start on concrete work, such as the curbs, some sidewalk replacement, or base patching in the coming weeks. If there is concrete work that affects your access to your driveway at night, we will notify you 48 hours in advance and provide (2) overnight parking passes. Please contact Nick Deming, City of Wauwatosa Construction Manager if additional parking passes are needed, ndeming@wauwatosa.net or (414) 479-3541.